Qinhui Liu, Laizheng Zhu, Zhijie Gao, Jilong Wang, Jiang Li*
CMC-Computers, Materials & Continua, Vol.78, No.1, pp. 811-843, 2024, DOI:10.32604/cmc.2023.046040
- 30 January 2024
Abstract To improve the productivity, the resource utilization and reduce the production cost of flexible job shops, this paper designs an improved two-layer optimization algorithm for the dual-resource scheduling optimization problem of flexible job shop considering workpiece batching. Firstly, a mathematical model is established to minimize the maximum completion time. Secondly, an improved two-layer optimization algorithm is designed: the outer layer algorithm uses an improved PSO (Particle Swarm Optimization) to solve the workpiece batching problem, and the inner layer algorithm uses an improved GA (Genetic Algorithm) to solve the dual-resource scheduling problem. Then, a rescheduling method… More >